Line 19: | Line 19: | ||
|projects={{Phabricator Project | |projects={{Phabricator Project | ||
|name=DC-Ops | |name=DC-Ops | ||
|entryDate=1555442286 | |||
}}{{Phabricator Project | }}{{Phabricator Project | ||
|name=Patch-For-Review | |name=Patch-For-Review | ||
|entryDate=1555442286 | |||
}}{{Phabricator Project | }}{{Phabricator Project | ||
|name=decommission | |name=decommission-hardware | ||
|column=pending onsite steps (codfw) | |column=pending onsite steps (codfw) | ||
|entryDate=1556043972 | |||
}} | |||
|transitions={{Transition | |||
|date=1558038613 | |||
|type=Added Project | |||
|project=Patch-For-Review | |||
}}{{Transition | |||
|date=1556043972 | |||
|type=Entered Column | |||
|project=decommission-hardware | |||
|column=pending onsite steps (codfw) | |||
}}{{Transition | |||
|date=1556043972 | |||
|type=Exited Column | |||
|project=decommission-hardware | |||
|column=Ready for Decommission | |||
}}{{Transition | |||
|date=1556042935 | |||
|type=Removed Project | |||
|project=Patch-For-Review | |||
}}{{Transition | |||
|date=1556042787 | |||
|type=Added Project | |||
|project=Patch-For-Review | |||
}}{{Transition | |||
|date=1555612768 | |||
|type=Entered Column | |||
|project=decommission-hardware | |||
|column=Ready for Decommission | |||
}}{{Transition | |||
|date=1555612768 | |||
|type=Exited Column | |||
|project=decommission-hardware | |||
|column=Blocked on Service Owners | |||
}}{{Transition | |||
|date=1555603824 | |||
|type=Entered Column | |||
|project=decommission-hardware | |||
|column=Blocked on Service Owners | |||
}}{{Transition | |||
|date=1555603824 | |||
|type=Exited Column | |||
|project=decommission-hardware | |||
|column=Backlog | |||
}}{{Transition | |||
|date=1555442286 | |||
|type=Added Project | |||
|project=decommission-hardware | |||
}}{{Transition | |||
|date=1555442286 | |||
|type=Added Project | |||
|project=DC-Ops | |||
}} | }} | ||
}} | }} |
Latest revision as of 13:12, 11 June 2020
Phabricator Link | T221134 |
---|---|
Status | resolved |
Priority | Medium (orange) |
Points | |
Phabricator Task Created | 2019/04/16 03:18 PM |
Wiki Page Created | 2019/06/09 01:19 PM |
Phabricator Task Last Modified | 2019/05/16 04:33 PM |
Wiki Page Last Updated | 2020/06/11 02:12 PM |
Phabricator Task Closed | 2019/05/16 04:33 PM |
Authored By | Dzahn (Daniel Zahn) |
Assigned To | Papaul (Papaul) |
Projects |
|
Platform Engineering Initiative Column | |
Platform Team Workboards Column | |
Subtasks | |
Parent Tasks |
Column Transitions: (Added project: ⇑, Removed project: ⇓,Entered column: ⇒, Exited column: ⇐)
Project | Column | Date |
---|---|---|
⇑ decommission-hardware | 16 April 2019 | |
⇑ DC-Ops | 16 April 2019 | |
decommission-hardware | ⇐ Backlog | 18 April 2019 |
decommission-hardware | ⇒ Blocked on Service Owners | 18 April 2019 |
decommission-hardware | ⇐ Blocked on Service Owners | 18 April 2019 |
decommission-hardware | ⇒ Ready for Decommission | 18 April 2019 |
⇑ Patch-For-Review | 23 April 2019 | |
⇓ Patch-For-Review | 23 April 2019 | |
decommission-hardware | ⇐ Ready for Decommission | 23 April 2019 |
decommission-hardware | ⇒ pending onsite steps (codfw) | 23 April 2019 |
⇑ Patch-For-Review | 16 May 2019 |