Difference between revisions of "T184054: Decommission db1029 and db1031"
From cpt
m (updated task from Phabricator) |
m (updated task from Phabricator) |
||
(One intermediate revision by the same user not shown) | |||
Line 22: | Line 22: | ||
|entryDate=1528956632 | |entryDate=1528956632 | ||
}}{{Phabricator Project | }}{{Phabricator Project | ||
|name= | |name=SRE | ||
|column=Backlog | |column=Backlog | ||
|entryDate=1514974885 | |entryDate=1514974885 | ||
}}{{Phabricator Project | }}{{Phabricator Project | ||
|name=decommission | |name=decommission-hardware | ||
|column=pending onsite steps (eqiad) | |column=pending onsite steps (eqiad) | ||
|entryDate=1528957592 | |entryDate=1528957592 | ||
Line 37: | Line 37: | ||
|date=1528957592 | |date=1528957592 | ||
|type=Entered Column | |type=Entered Column | ||
|project=decommission | |project=decommission-hardware | ||
|column=pending onsite steps (eqiad) | |column=pending onsite steps (eqiad) | ||
}}{{Transition | }}{{Transition | ||
|date=1528957592 | |date=1528957592 | ||
|type=Exited Column | |type=Exited Column | ||
|project=decommission | |project=decommission-hardware | ||
|column=Backlog | |column=Backlog | ||
}}{{Transition | }}{{Transition | ||
Line 75: | Line 75: | ||
|date=1525388327 | |date=1525388327 | ||
|type=Added Project | |type=Added Project | ||
|project=decommission | |project=decommission-hardware | ||
}}{{Transition | }}{{Transition | ||
|date=1524605463 | |date=1524605463 |
Latest revision as of 12:04, 6 January 2021
Phabricator Link | T184054 |
---|---|
Status | resolved |
Priority | Medium (orange) |
Points | |
Phabricator Task Created | 2018/01/03 05:21 AM |
Wiki Page Created | 2019/06/09 01:23 PM |
Phabricator Task Last Modified | 2018/06/26 12:44 PM |
Wiki Page Last Updated | 2021/01/06 12:04 PM |
Phabricator Task Closed | 2018/06/26 12:44 PM |
Authored By | jcrespo (Jaime Crespo) |
Assigned To | Cmjohnson (cmjohnson) |
Projects |
|
Platform Engineering Initiative Column | |
Platform Team Workboards Column | |
Subtasks | |
Parent Tasks |
Column Transitions: (Added project: ⇑, Removed project: ⇓,Entered column: ⇒, Exited column: ⇐)
Project | Column | Date |
---|---|---|
DBA | ⇐ Triage | 3 January 2018 |
DBA | ⇒ In progress | 3 January 2018 |
DBA | ⇐ In progress | 19 January 2018 |
DBA | ⇒ Blocked external/Not db team | 19 January 2018 |
DBA | ⇐ Blocked external/Not db team | 19 January 2018 |
DBA | ⇒ Done | 19 January 2018 |
ops-eqiad | ⇐ Backlog | 26 January 2018 |
ops-eqiad | ⇒ Decommission | 26 January 2018 |
hardware-requests | ⇐ Backlog | 1 February 2018 |
hardware-requests | ⇒ Reclaim (Spares/Decommission) | 1 February 2018 |
hardware-requests | ⇐ Reclaim (Spares/Decommission) | 15 March 2018 |
hardware-requests | ⇒ Reclaim (Spares/Decommission) | 15 March 2018 |
ops-eqiad | ⇐ Decommission | 4 April 2018 |
ops-eqiad | ⇒ Decommission | 4 April 2018 |
⇑ Patch-For-Review | 24 April 2018 | |
ops-eqiad | ⇐ Decommission | 24 April 2018 |
ops-eqiad | ⇒ High Priority Task | 24 April 2018 |
ops-eqiad | ⇐ High Priority Task | 24 April 2018 |
ops-eqiad | ⇒ Up next | 24 April 2018 |
⇓ hardware-requests | 3 May 2018 | |
⇓ Patch-For-Review | 3 May 2018 | |
⇑ decommission-hardware | 3 May 2018 | |
ops-eqiad | ⇐ Up next | 7 May 2018 |
ops-eqiad | ⇒ High Priority Task | 7 May 2018 |
DBA | ⇐ Done | 14 June 2018 |
DBA | ⇒ Done | 14 June 2018 |
decommission-hardware | ⇐ Backlog | 14 June 2018 |
decommission-hardware | ⇒ pending onsite steps (eqiad) | 14 June 2018 |