Difference between revisions of "T183745: FY17/18 Q3 Program 7 Services Goal: Full migration to Cassandra 3"

From cpt
m (updated task from Phabricator)
m (updated task from Phabricator)
 
(6 intermediate revisions by the same user not shown)
Line 3: Line 3:
|status=resolved
|status=resolved
|color=orange
|color=orange
|points=
|dateCreated=1514466032
|dateCreated=1514466032
|dateModified=1563480674
|dateModified=1565628088
|dateClosed=1563480674
|dateClosed=1563480674
|author={{Phabricator User
|author={{Phabricator User
Line 19: Line 20:
|name=Cassandra
|name=Cassandra
|column=Backlog
|column=Backlog
|entryDate=1514466032
}}{{Phabricator Project
}}{{Phabricator Project
|name=Goal
|name=Goal
|entryDate=1514466032
}}{{Phabricator Project
}}{{Phabricator Project
|name=RESTBase-Cassandra
|name=RESTBase-Cassandra
|column=Backlog
|column=Backlog
|entryDate=1514466032
}}{{Phabricator Project
}}{{Phabricator Project
|name=RESTBase
|name=RESTBase
|column=Backlog
|column=Backlog
|entryDate=1514466032
}}{{Phabricator Project
}}{{Phabricator Project
|name=Core Platform Team Workboards (Team 2)
|name=Platform Team Workboards (Team 2)
|column=Product Acceptance
|column=Product Acceptance
|entryDate=1562354541
}}{{Phabricator Project
}}{{Phabricator Project
|name=User-Eevans
|name=User-Eevans
|column=Backlog
|column=Backlog
|entryDate=1514466032
}}{{Phabricator Project
}}{{Phabricator Project
|name=Services
|name=Services
|column=done
|column=done
|entryDate=1514466032
}}
}}
|subtasks=184110,181964,189057,187255,186656,185089,184199,184100,179419,178177
|subtasks=184110,181964,189057,187255,186656,185089,184199,184100,179419,178177
|transitions={{Transition
|date=1562354541
|type=Entered Column
|project=Platform Team Workboards (Team 2)
|column=Product Acceptance
}}{{Transition
|date=1562354541
|type=Exited Column
|project=Platform Team Workboards (Team 2)
|column=Backlog
}}{{Transition
|date=1562354534
|type=Removed Project
|project=Platform Team Workboards (Done with CPT)
}}{{Transition
|date=1562354534
|type=Added Project
|project=Platform Team Workboards (Team 2)
}}{{Transition
|date=1562354534
|type=Entered Column
|project=Platform Team Workboards
|column=Team 2
}}{{Transition
|date=1562354534
|type=Exited Column
|project=Platform Team Workboards
|column=Done with CPT
}}{{Transition
|date=1553787550
|type=Removed Project
|project=Platform Team Workboards (Doing)
}}{{Transition
|date=1553787550
|type=Removed Project
|project=Services (doing)
}}{{Transition
|date=1553787550
|type=Added Project
|project=Services (done)
}}{{Transition
|date=1553787550
|type=Added Project
|project=Platform Team Workboards (Done with CPT)
}}{{Transition
|date=1545309791
|type=Added Project
|project=Platform Team Workboards (Doing)
}}
}}
}}

Latest revision as of 15:41, 17 July 2020

Phabricator Link T183745
Status resolved
Priority Medium (orange)
Points
Phabricator Task Created 2017/12/28 08:00 AM
Wiki Page Created 2019/06/09 01:25 PM
Phabricator Task Last Modified 2019/08/12 12:41 PM
Wiki Page Last Updated 2020/07/17 04:41 PM
Phabricator Task Closed 2019/07/18 04:11 PM
Authored By mobrovac (Marko Obrovac)
Assigned To Eevans (Eric Evans)
Projects
Platform Engineering Initiative Column
Platform Team Workboards Column Team 2: Product Acceptance
Subtasks
Parent Tasks


Column Transitions: (Added project: ⇑, Removed project: ⇓,Entered column: ⇒, Exited column: ⇐)

Project Column Date
Platform Team Workboards (Doing) 20 December 2018
Platform Team Workboards (Doing) 28 March 2019
Services (doing) 28 March 2019
Platform Team Workboards (Done with CPT) 28 March 2019
Services (done) 28 March 2019
Platform Team Workboards (Done with CPT) 5 July 2019
Platform Team Workboards Done with CPT 5 July 2019
Platform Team Workboards Team 2 5 July 2019
Platform Team Workboards (Team 2) 5 July 2019
Platform Team Workboards (Team 2) Backlog 5 July 2019
Platform Team Workboards (Team 2) Product Acceptance 5 July 2019